US data-center projects, checked against filings
95 GW of projects carry a megawatt figure we can source. 23 GW of it is under construction.
Nameplate tracks 619 projects in 33 states. We book a megawatt or dollar figure only when a filing, permit or company disclosure supports it for that site. 464 projects have no megawatt figure we will book.
Where the 95 GW stands
Sourced megawatts by stage, from 155 projects with a megawatt figure- Operating or partly operating8.3 GW228 projects in this stage
- Building23.4 GW103 projects in this stage
- Permitting29.9 GW135 projects in this stage
- Proposed30.2 GW127 projects in this stage
- Cancelled or delayed3.1 GW26 projects in this stage
Map of projects
- Operating or partly operating
- Building
- Permitting
- Proposed
- Cancelled or delayed
- Not classified
- Disputed
- County-level location
What changed
Newest firstPrologis Trenton Data Center. Prologis sued Trenton on Thursday, Nov. 12, in the U.S. District Court for the Southern District of Ohio, arguing the voter-approved ban covers only future projects of 25 MW or more. Prologis is building a nearly 900,000 square foot, 250 MW Amazon Web Services data center.
Journal-NewsPrologis Trenton Data Center. Prologis sued Trenton over the voter-approved amendment barring data centers over 25 MW. The suit says applying the ban to a project that was already vested, permitted and largely built would be unconstitutional.
WVXUAmazon Sunbury Data Center. 10TV reported Sunbury voters passing the limit on large data centers with 78.64% in unofficial returns, and carried a statement from an Amazon spokesperson.
10TVAWS Madison and St. Clair Townships Project. Trenton voters banned data centers above 25 MW within city limits. The Journal-News says the ban should not affect a four-building AWS data center under construction on 141 acres, and could affect a proposed 18-building AWS project tied to 600 acres in Madison and St. Clair townships.
Journal-NewsPrologis Trenton Data Center. Trenton voters banned data centers above 25 MW within city limits. The Journal-News says the ban should not affect a four-building AWS data center under construction on 141 acres, and could affect a proposed 18-building AWS project tied to 600 acres in Madison and St. Clair townships.
Journal-NewsProject Jupiter. Doña Ana County commissioners voted 5-0 on Oct. 27, after more than two hours in closed session, to authorize county management and counsel to notify the Project Jupiter entities of a potential breach of the industrial revenue bond agreements over the campus's proposed connection to El Paso Electric, and to open talks.
Organ Mountain NewsProject Jupiter. Doña Ana County commissioners appointed 11 residents to the Project Jupiter Community Monitoring Committee, created by an Aug. 11 resolution.
KFOX14Project Jupiter. At the Oct. 13 county commission meeting, Oracle said a proposed El Paso Electric connection would supply less than 3% of the campus's power, mainly for construction, commissioning and emergency backup.
Organ Mountain News
Coming up
Dated decisionsEnd of Hayward's initial data center moratorium term, unless extended. Hayward City Council
City of HaywardProject Jupiter. Public hearing on the Project Jupiter air permits opens at 9 a.m., Sunland Park Multi-Generational Center, first day public comment; reported as weeklong New Mexico Environment Department
Source NMReport by ERCOT and the PUCT on the governor's data center RFI, due on or before Dec. 10, 2026 PUCT / ERCOT
ERCOTEnd of Pittsburg's 45-day data center moratorium adopted Oct. 26, unless extended. Pittsburg City Council
NBC Bay AreaEnd of San Diego's 45-day data center moratorium adopted Oct. 27, unless extended. San Diego City Council
The San Diego Union-TribuneEnd of Cumberland County's six-month data center moratorium for its unincorporated areas. Cumberland County Board of Commissioners
CityView
Companies
Start from the name you follow| Company | Ticker | Sites tracked | Latest |
|---|---|---|---|
| Amazon | AMZN | 80 | Prologis sued Trenton on Thursday, Nov. 12, in the U.S. District Court for the Southern District of Ohio, arguing the voter-approved ban covers only future projects of 25 MW or more. Prologis is building a nearly 900,000 square foot, 250 MW Amazon Web Services data center.Journal-News |
| Microsoft | MSFT | 40 | News reported.GeekWire |
| Alphabet Inc. (Google) | GOOGL | 30 | Announcement.storage.googleapis.com |
| Meta | META | 22 | Ownership structure disclosed.elpasomatters.org |
| CoreWeave, Inc. | CRWV | 2 | Announcement.Core Scientific |
| Oracle Corporation | ORCL | 2 | Doña Ana County commissioners voted 5-0 on Oct. 27, after more than two hours in closed session, to authorize county management and counsel to notify the Project Jupiter entities of a potential breach of the industrial revenue bond agreements over the campus's proposed connection to El Paso Electric, and to open talks.Organ Mountain News |