CoreWeave, Inc. CRWV
2 sites in the book. 1 operating or partly operating, 1 building.
- Megawatts we can source
- 453 MWacross 2 of 2 sites
- Megawatts at disputed sites
- 0 MWNo site has an open dispute
- Next dated decision
- Not on file
Sourced megawatts by stage: Operating or partly operating 153 MW. Building 300 MW.
Sites
Largest sourced megawatts first| Site | Stage | MW | Power | Money | Open issue or next date |
|---|---|---|---|---|---|
| CoreWeave Lancaster Data CenterLancaster County, PA · Tenant | Building | 300 MW | PPL Electric Utilities territory contextOn file, no public link | $6B corporate investmentAnnounced, not a financing recordData Center Dynamics | Not on file |
| Core Scientific Port MuskogeeMuskogee County, OK · Tenant | Partly operating | 152.5 MW | OG&E (Oklahoma Gas & Electric; NYSE OGE) -- electric service agreements up to 440MW gross + an on-site substationData Center Dynamics | $421M asset acquisition costCommittedData Center Dynamics | Not on file |
Map of sites
- Operating or partly operating
- Building
- Permitting
- Proposed
- Cancelled or delayed
- Not classified
- Disputed
- County-level location
Financing picture
Sourced facts per site. "Not on file" means we have no record, not that it is missing.- Committed financing: $421M
- Announced capex: $6.4B
66% of sourced megawatts involve Chirisa Technology Parks.
| Site | Money on file | Who is on the hook | Power | Permits | Disputes |
|---|---|---|---|---|---|
| CoreWeave Lancaster Data Center | $6B corporate investmentAnnounced, not a financing recordData Center Dynamics | Developer: Chirisa Technology Parks. Tenant: CoreWeave, Inc.. Developer: Machine Investment GroupData Center Dynamics | PPL Electric Utilities territory contextOn file, no public link | 0 of 1 checked permits passed. Air permit pendingPennsylvania Bulletin | Not on file |
| Core Scientific Port Muskogee | $421M asset acquisition costCommittedData Center Dynamics | Operator: Core Scientific. Tenant: CoreWeave, Inc.Data Center Dynamics | OG&E (Oklahoma Gas & Electric; NYSE OGE) -- electric service agreements up to 440MW gross + an on-site substationData Center Dynamics | 0 of 1 checked permits passed. Power interconnection pendingData Center Dynamics | Not on file |
Who holds the paper
Not on file
What changed
Newest firstCore Scientific Port Muskogee. Announcement.
Core ScientificCoreWeave Lancaster Data Center. News reported.
Data Center Dynamics
Coming up
Dated decisionsNot on file
What we refused
Not on file
Alerts are not live yet. We will keep your email only to send them when they start.