Microsoft MSFT

40 sites in the book. 14 operating or partly operating, 8 building, 10 permitting, 8 proposed.

Megawatts we can source
2,484 MWacross 7 of 40 sites
Megawatts at disputed sites
0 MWNo site has an open dispute
Next dated decision
Not on file

Sourced megawatts by stage: Operating or partly operating 400 MW. Building 1,875 MW. Permitting 209 MW.

Sites

Largest sourced megawatts first
SiteStageMWPowerMoneyOpen issue or next date
Crusoe Microsoft AbileneTaylor County, TX · AI compute customer Building 900 MW behind-the-meter dedicated on-site powerCrusoe Energy Systems $384M estimated cost filed with Texas TDLRAnnounced, not a financing recordTexas Department of Licensing and Regulation Not on file
Microsoft Ginger East Data CenterWarren County, IA · Owner Building 444 MW MidAmerican EnergyOn file, no public link $1B developer announced investmentAnnounced, not a financing recordDataCenterDynamics Not on file
Microsoft Fairwater, Mount PleasantRacine County, WI · Sponsor Partly operating 400 MW We Energieswww.wpr.org $4B self-funded by the sponsorAnnounced, not a financing recordapps.psc.wi.gov Not on file
Microsoft Union City Data CenterFulton County, GA · Tenant Building 324 MW Georgia Power territory context (not project-specific interconnect evidence)On file, no public link $1.8B corporate investmentAnnounced, not a financing recordData Center Frontier Not on file
Microsoft Ginger West Data CenterDallas County, IA · Owner Building 207 MW MidAmerican EnergyOn file, no public link $1B developer announced investmentAnnounced, not a financing recordDataCenterDynamics Not on file
Microsoft Ruthenium Data CenterMadison County, IA · Owner Permitting 113 MW MidAmerican EnergyOn file, no public link $15.3M real estate acquisitionCommittedBusiness Record Not on file
Microsoft Tyrone Project RitaFayette County, GA · Owner Permitting 96 MW Georgia Power (Fayette County territory)DataCenterDynamics $350M developer announced investmentAnnounced, not a financing recordThe Atlanta Journal-Constitution Not on file
Microsoft BeckerSherburne County, MN · Owner Proposed Refused Xcel Energy (NASDAQ XEL -- sold Microsoft the land near the Sherco coal plant)MPR News $17.7M land acquisition costCommittedMPR News Not on file
Microsoft Blue Ridge IAD11-13Loudoun County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton AVCMecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton AVC09Mecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton AVC17Mecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton AVC43Mecklenburg County, VA · Operator Permitting Not on file Not on file Not on file Not on file
Microsoft Boydton East CoastMecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton LVLMecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Boydton LYH03Mecklenburg County, VA · Operator Permitting Not on file Not on file Not on file Not on file
Microsoft Boydton LYH10Mecklenburg County, VA · Operator Permitting Not on file Not on file Not on file Not on file
Microsoft Boydton TimberMecklenburg County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Catawba County Data Center CampusCatawba County, NC · Developer Proposed Not on file Grid, under construction contextOn file, no public link $1B sponsor equityAnnounced, not a financing recordDataCenterDynamics Not on file
Microsoft Cherry Valley Data CenterBoone County, IL · Owner Permitting Refused ComEd (Commonwealth Edison) / PJM ComEd ZoneOn file, no public link $250M developer announced investmentAnnounced, not a financing recordGrowth Dimensions Economic Development Not on file
Microsoft CheyenneLaramie County, WY · Operator Operating Refused Black Hills Energy (BKH) via the LPCS large-load tariffOil City News $274M expansion capexAnnounced, not a financing recordLerch Bates Not on file
Microsoft Douglasville Data CenterDouglas County, GA · Owner Building Refused Grid, no interconnect evidenceOn file, no public link $13.8M real estate acquisitionCommittedDataCenterDynamics Not on file
Microsoft East Point Data CenterFulton County, GA · Owner Building Refused Georgia Power (Fulton County territory)DataCenterDynamics $420M industrial revenue bondAnnounced, not a financing recordDataCenterDynamics Not on file
Microsoft FairwaterFayette County, GA · Tenant Proposed Refused Grid, operating power contextOn file, no public link $154M real estate acquisitionCommittedAtlanta Journal-Constitution Not on file
Microsoft Fauquier CountyFauquier County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Gainesville MNZ03Prince William County, VA · Operator Permitting Not on file Not on file Not on file Not on file
Microsoft La PorteLaPorte County, IN · Owner Proposed Refused Grid, no interconnect evidenceOn file, no public link $1B corporate investmentAnnounced, not a financing recordIndiana Economic Development Corporation Not on file
Microsoft Leesburg IAD01-05Loudoun County, VA · Operator Operating Not on file Not on file Not on file Not on file
Microsoft Malaga Data CenterChelan County, WA · Operator Building Not on file Chelan County PUD (large-load contract / Rate Schedule 36); 2026-2040 third-party clean power from outside the regionChelan County PUD $86.5M sponsor grid infrastructureCommittedChelan County PUD Not on file
Microsoft - Manassas Data Center - MNZ01Prince William County, VA · Operator Permitting Not on file Not on file Not on file Not on file
Microsoft Palmetto Data CenterFulton County, GA · Owner Building Refused Grid, no interconnect evidenceOn file, no public link $6M real estate acquisitionCommittedDataCenterDynamics Not on file
Microsoft Person County Mega Park Data Center CampusPerson County, NC · Developer Proposed Not on file Customer cost protection context, early stage power contextOn file, no public link $26.8M real estate acquisitionCommittedDataCenterDynamics Not on file
Microsoft Plano Data CenterKendall County, IL · Owner Permitting Refused ComEd (Commonwealth Edison) / PJM ComEd ZoneOn file, no public link Not on file Not on file
Microsoft Quincy Data CenterGrant County, WA · Operator Operating Not on file Grant County PUDOn file, no public link $11M real estate acquisitionCommittedData Center Knowledge Not on file
Microsoft Rome Project FirecrackerFloyd County, GA · Owner Proposed Refused Announced campus context, gridOn file, no public link $1B corporate investmentAnnounced, not a financing recordDataCenterDynamics Not on file
Microsoft San AntonioBexar County, TX · Owner Partly operating Not on file CPS EnergyOn file, no public link $400M reported construction costAnnounced, not a financing recordBisnow Not on file
Microsoft Silver Springs Data Center CampusLyon County, NV · Owner Proposed Not on file Grid, no interconnect evidenceOn file, no public link $16.4M real estate acquisitionCommittedDataCenterDynamics Not on file
Microsoft St Joe Farm MishawakaSt. Joseph County, IN · Owner Permitting Refused Grid, no interconnect evidenceOn file, no public link $77.5M site acquisition costCommittedData Center Dynamics Not on file
Microsoft West Des Moines Data Center CampusPolk County, IA · Owner Operating Not on file MidAmerican EnergyOn file, no public link $5B corporate investmentAnnounced, not a financing recordMicrosoft Local Not on file
Microsoft West US 3 Arizona Data Center RegionMaricopa County, AZ · Operator Proposed Refused GridOn file, no public link $131M real estate acquisitionCommittedDataCenterDynamics Not on file

Map of sites

  • Operating or partly operating
  • Building
  • Permitting
  • Proposed
  • Cancelled or delayed

Financing picture

Sourced facts per site. "Not on file" means we have no record, not that it is missing.
  • Committed financing: $556.1M
  • Bond ceilings and authorizations: $12.6M
  • Announced capex: $18.8B
SiteMoney on fileWho is on the hookPowerPermitsDisputes
Crusoe Microsoft Abilene $384M estimated cost filed with Texas TDLRAnnounced, not a financing recordTexas Department of Licensing and Regulation Developer/operator: Crusoe Energy Systems. AI compute customer: MicrosoftCrusoe Energy Systems behind-the-meter dedicated on-site powerCrusoe Energy Systems 1 of 1 checked permits passedTexas Department of Licensing and Regulation Not on file
Microsoft Ginger East Data Center $1B developer announced investmentAnnounced, not a financing recordDataCenterDynamics Owner: MicrosoftMicrosoft Local MidAmerican EnergyOn file, no public link 1 of 2 checked permits passed. Air permit pendingBusiness Record · Iowa Department of Natural Resources Not on file
Microsoft Fairwater, Mount Pleasant $4B self-funded by the sponsorAnnounced, not a financing recordapps.psc.wi.gov Operator: Microsoft. Sponsor: Microsoft. Tenant: Microsoftblogs.microsoft.com We Energieswww.wpr.org 1 of 2 checked permits passed. Air permit pendingdnr.wisconsin.gov · apps.psc.wi.gov Not on file
Microsoft Union City Data Center $1.8B corporate investmentAnnounced, not a financing recordData Center Frontier Developer: EdgeConneX. Tenant: Microsoft. Developer: TA RealtyData Center Frontier Georgia Power territory context (not project-specific interconnect evidence)On file, no public link 1 of 1 checked permits passedData Center Frontier Not on file
Microsoft Ginger West Data Center $1B developer announced investmentAnnounced, not a financing recordDataCenterDynamics Owner: MicrosoftMicrosoft Local MidAmerican EnergyOn file, no public link 1 of 1 checked permits passedDataCenterDynamics Not on file
Microsoft Ruthenium Data Center $15.3M real estate acquisitionCommittedBusiness Record Owner: MicrosoftBusiness Record MidAmerican EnergyOn file, no public link 1 of 1 checked permits passedWest Des Moines Water Works Not on file
Microsoft Tyrone Project Rita $350M developer announced investmentAnnounced, not a financing recordThe Atlanta Journal-Constitution Owner: MicrosoftDataCenterDynamics Georgia Power (Fayette County territory)DataCenterDynamics 1 of 1 checked permits passedData Center Dynamics Not on file
Microsoft Becker $17.7M land acquisition costCommittedMPR News Owner: MicrosoftMPR News Xcel Energy (NASDAQ XEL -- sold Microsoft the land near the Sherco coal plant)MPR News Not on file Not on file
Microsoft Blue Ridge IAD11-13 Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton AVC Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton AVC09 Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton AVC17 Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton AVC43 Not on file Operator: MicrosoftVirginia DEQ Not on file 1 of 1 checked permits passedCommonwealth of Virginia (2026 Appropriations Act) Not on file
Microsoft Boydton East Coast Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton LVL Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Boydton LYH03 Not on file Operator: MicrosoftVirginia DEQ Not on file 1 of 1 checked permits passedCommonwealth of Virginia (2026 Appropriations Act) Not on file
Microsoft Boydton LYH10 Not on file Operator: MicrosoftVirginia DEQ Not on file 1 of 1 checked permits passedCommonwealth of Virginia (2026 Appropriations Act) Not on file
Microsoft Boydton Timber Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Catawba County Data Center Campus $1B sponsor equityAnnounced, not a financing recordDataCenterDynamics Developer: MicrosoftDataCenterDynamics Grid, under construction contextOn file, no public link 1 of 1 checked permits passedCatawba County, North Carolina Not on file
Microsoft Cherry Valley Data Center $250M developer announced investmentAnnounced, not a financing recordGrowth Dimensions Economic Development Owner: MicrosoftDataCenterDynamics ComEd (Commonwealth Edison) / PJM ComEd ZoneOn file, no public link 1 of 1 checked permits passedVillage of Cherry Valley, Illinois Not on file
Microsoft Cheyenne $274M expansion capexAnnounced, not a financing recordLerch Bates Operator: MicrosoftMicrosoft Black Hills Energy (BKH) via the LPCS large-load tariffOil City News Not on file Not on file
Microsoft Douglasville Data Center $13.8M real estate acquisitionCommittedDataCenterDynamics Owner: MicrosoftDataCenterDynamics Grid, no interconnect evidenceOn file, no public link 0 of 1 checked permits passed. Environmental review pendingDataCenterDynamics Not on file
Microsoft East Point Data Center $420M industrial revenue bondAnnounced, not a financing recordDataCenterDynamics Owner: MicrosoftDataCenterDynamics Georgia Power (Fulton County territory)DataCenterDynamics 0 of 1 checked permits passed. Air permit pendingGeorgia Department of Natural Resources Not on file
Microsoft Fairwater $154M real estate acquisitionCommittedAtlanta Journal-Constitution Parent: Blackstone Inc.. Tenant: Microsoft. Developer: QTSwww.ajc.com · blogs.microsoft.com Grid, operating power contextOn file, no public link 1 of 1 checked permits passedTown of Tyrone, Georgia Not on file
Microsoft Fauquier County Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Gainesville MNZ03 Not on file Operator: MicrosoftVirginia DEQ Not on file 1 of 1 checked permits passedCommonwealth of Virginia (2026 Appropriations Act) Not on file
Microsoft La Porte $1B corporate investmentAnnounced, not a financing recordIndiana Economic Development Corporation Owner: MicrosoftIndiana Economic Development Corp (IEDC) Grid, no interconnect evidenceOn file, no public link 1 of 1 checked permits passedABC57 Not on file
Microsoft Leesburg IAD01-05 Not on file Operator: MicrosoftVirginia DEQ Not on file Not on file Not on file
Microsoft Malaga Data Center $86.5M sponsor grid infrastructureCommittedChelan County PUD Operator: MicrosoftChelan County PUD Chelan County PUD (large-load contract / Rate Schedule 36); 2026-2040 third-party clean power from outside the regionChelan County PUD 1 of 1 checked permits passedChelan County PUD Not on file
Microsoft - Manassas Data Center - MNZ01 Not on file Operator: MicrosoftVirginia DEQ Not on file 1 of 1 checked permits passedCommonwealth of Virginia (2026 Appropriations Act) Not on file
Microsoft Palmetto Data Center $6M real estate acquisitionCommittedDataCenterDynamics Owner: MicrosoftDataCenterDynamics Grid, no interconnect evidenceOn file, no public link Not on file Not on file
Microsoft Person County Mega Park Data Center Campus $26.8M real estate acquisitionCommittedDataCenterDynamics Developer: MicrosoftDataCenterDynamics Customer cost protection context, early stage power contextOn file, no public link Not on file Not on file
Microsoft Plano Data Center Not on file Owner: MicrosoftShaw Local / Kendall County Now ComEd (Commonwealth Edison) / PJM ComEd ZoneOn file, no public link 1 of 1 checked permits passedData Center Dynamics Not on file
Microsoft Quincy Data Center $11M real estate acquisitionCommittedData Center Knowledge Operator: MicrosoftGeekWire Grant County PUDOn file, no public link 1 of 1 checked permits passedWashington State Department of Ecology Not on file
Microsoft Rome Project Firecracker $1B corporate investmentAnnounced, not a financing recordDataCenterDynamics Owner: MicrosoftDataCenterDynamics Announced campus context, gridOn file, no public link 1 of 1 checked permits passedDataCenterDynamics Not on file
Microsoft San Antonio $400M reported construction costAnnounced, not a financing recordBisnow Owner: MicrosoftMicrosoft CPS EnergyOn file, no public link 1 of 1 checked permits passedTexas Department of Licensing and Regulation Not on file
Microsoft Silver Springs Data Center Campus $16.4M real estate acquisitionCommittedDataCenterDynamics Owner: MicrosoftDataCenterDynamics Grid, no interconnect evidenceOn file, no public link 1 of 1 checked permits passedDataCenterDynamics Not on file
Microsoft St Joe Farm Mishawaka $77.5M site acquisition costCommittedData Center Dynamics Owner: MicrosoftData Center Dynamics Grid, no interconnect evidenceOn file, no public link 1 of 1 checked permits passedWNDU Not on file
Microsoft West Des Moines Data Center Campus $5B corporate investmentAnnounced, not a financing recordMicrosoft Local Owner: MicrosoftMicrosoft Local MidAmerican EnergyOn file, no public link 1 of 1 checked permits passedCity of West Des Moines, Iowa Not on file
Microsoft West US 3 Arizona Data Center Region $131M real estate acquisitionCommittedDataCenterDynamics Operator: MicrosoftDataCenterDynamics GridOn file, no public link Not on file Not on file

Who holds the paper

Not on file

What changed

Newest first

Coming up

Dated decisions

Not on file

What we refused

  • Microsoft Tyrone Project Rita: we did not book a cost figure from this source.The source does not state a cost for this site alone.Data Center Dynamics
  • Microsoft Cherry Valley Data Center: we did not book a cost figure from this source.The reviewed reporting supports Microsoft Cherry Valley project identity and county context, but does not disclose a project-specific dollar amount.DataCenterDynamics
  • Microsoft Plano Data Center: we did not book a cost figure from this source.The reviewed source reports a planned 500-acre acquisition and rezoning context, but no land price or project capex amount.Data Center Dynamics
  • Microsoft Becker: we did not book a megawatt figure from this source.Local evidence records Microsoft land acquisition near Sherco and Xcel utility context, but no city project filing, load request, or site MW.MPR News
  • Microsoft East Point Data Center: we did not book a megawatt figure from this source.Linked evidence records Project Fulton/East Point, $420M investment, two buildings, and on-site substation context; no site or interconnect MW is disclosed.DataCenterDynamics
  • Microsoft Cheyenne: we did not book a megawatt figure from this source.The linked source records a 3,200-acre expansion, Black Hills large-load tariff context, and backup-generator permitting, but no project/site MW.Oil City News
  • Microsoft Douglasville Data Center: we did not book a megawatt figure from this source.The linked source records four 245,000-square-foot technology facilities on a 160-acre parcel, but no project/site MW.DataCenterDynamics
  • Microsoft Palmetto Data Center: we did not book a megawatt figure from this source.The linked source records Microsoft construction at Palmetto and prior 250,000-square-foot site context, but no project/site MW.DataCenterDynamics
  • Microsoft Rome Project Firecracker: we did not book a megawatt figure from this source.The linked source records a $1B, 347-acre Microsoft campus and Georgia power-context gaps, but no project/site MW.DataCenterDynamics
  • Microsoft Fairwater: we did not book a megawatt figure from this source.The linked evidence records AI superfactory architecture, QTS campus context, water-use events, and Georgia Power/on-site-generation context. It explicitly withholds total facility MW.blogs.microsoft.com
  • Microsoft La Porte: we did not book a megawatt figure from this source.The linked source records a $1B, 245,000-square-foot data center on 489 acres and expansion context, but no project/site MW.Indiana Economic Development Corp (IEDC)
  • Microsoft St Joe Farm Mishawaka: we did not book a megawatt figure from this source.The linked evidence records 939 acres, five to six buildings, and planning/MOU context, but no project/site MW.Data Center Dynamics
  • Microsoft Cherry Valley Data Center: we did not book a megawatt figure from this source.The linked trade source establishes the six-building Cherry Valley campus plan and entitlement timeline, but no project/site MW value.DataCenterDynamics
  • Microsoft Plano Data Center: we did not book a megawatt figure from this source.The source does not state the data center's own megawatts.Shaw Local / Kendall County Now
  • Microsoft West US 3 Arizona Data Center Region: we did not book a megawatt figure from this source.The DCD source covers an Azure region across Goodyear/El Mirage/Phoenix and related renewable procurement; it does not disclose per-site MW.DataCenterDynamics

Alerts are not live yet. We will keep your email only to send them when they start.