Prologis Trenton Data Center

Butler County, OH

Stage
Building, disputed
Megawatts
250 MW
Money
$7.8M real estate acquisitionCommittedLocal12 / WKRC
Next date
Not on file

Site map

  • Operating or partly operating
  • Building
  • Permitting
  • Proposed
  • Cancelled or delayed

Power

  • Duke Energy OhioOn file, no public link
  • GridOn file, no public link

Money

  • $7.8M real estate acquisitionCommittedLocal12 / WKRC
  • $7.8M real estate acquisitionCommittedLocal 12
  • $7.8M real estate acquisition costAnnounced, not a financing recordLocal 12

Who is on the hook

On-site equipment

Not on file

Permits and courts

  • Zoning and land use: passedLocal 12
  • Ruling on Prologis's suit over whether Trenton's Issue 17 can reach the permitted project: No date publishedJournal-News

What we refused

Not on file

Timeline

Newest first
  • Prologis sued Trenton on Thursday, Nov. 12, in the U.S. District Court for the Southern District of Ohio, arguing the voter-approved ban covers only future projects of 25 MW or more. Prologis is building a nearly 900,000 square foot, 250 MW Amazon Web Services data center.

    Journal-News
  • Prologis sued Trenton over the voter-approved amendment barring data centers over 25 MW. The suit says applying the ban to a project that was already vested, permitted and largely built would be unconstitutional.

    WVXU
  • Trenton voters banned data centers above 25 MW within city limits. The Journal-News says the ban should not affect a four-building AWS data center under construction on 141 acres, and could affect a proposed 18-building AWS project tied to 600 acres in Madison and St. Clair townships.

    Journal-News
  • Capacity disclosed.

    Local12 / WKRC