NAMEPLATE

Microsoft Cheyenne

Laramie County, WY

Stage
Operating
Megawatts
RefusedThe linked source records a 3,200-acre expansion, Black Hills large-load tariff context, and backup-generator permitting, but no project/site MW.
Money
$274M expansion capexAnnounced, not a financing recordLerch Bates
Next date
Not on file

Site map

  • Operating or partly operating
  • Building
  • Permitting
  • Proposed
  • Cancelled or delayed

Power

  • Black Hills Energy (BKH) via the LPCS large-load tariffOil City News

Money

  • $274M expansion capexAnnounced, not a financing recordLerch Bates
  • $68M off-site infrastructure obligationAnnounced, not a financing recordMicrosoft

Who is on the hook

  • Operator: MicrosoftCredit rating on file: AAAMicrosoft

On-site equipment

Not on file

Permits and courts

What we refused

  • We did not book a megawatt figure from this source.The linked source records a 3,200-acre expansion, Black Hills large-load tariff context, and backup-generator permitting, but no project/site MW.Oil City News