NAMEPLATE

Google Stillwater

Payne County, OK

Stage
Building
Megawatts
RefusedThe source records OG&E electric service agreements for Google sites and customer-funded interconnection costs, but no site-specific MW value.
Money
$3B corporate investmentAnnounced, not a financing recordGoogle (The Keyword)
Next date
Not on file

Site map

  • Operating or partly operating
  • Building
  • Permitting
  • Proposed
  • Cancelled or delayed

Power

  • OG&E (NYSE OGE) -- signed electric-service agreement (2026-04-30); Google pays 100% of interconnection costsOklahoma Business Voice

Money

Who is on the hook

On-site equipment

Not on file

Permits and courts

What we refused

  • We did not book a megawatt figure from this source.The source records OG&E electric service agreements for Google sites and customer-funded interconnection costs, but no site-specific MW value.Oklahoma Business Voice

Timeline

Newest first

Alerts are not live yet. We will keep your email only to send them when they start.